Project Duration
Stipulated Date of Commencement
July 08 2008
Stipulated Date of Completion /
Likely Date of Completion October 07 2009
Likely Date of Completion October 07 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 149,211,856.00
Awarded for
₹ 191,699,335.00
Project highlights
Road widening and hotmixing of internal and main roads, construction of drains with precast RCC covers, Footpath with pavers etc. Constructio of seating on foopath along the main road. Renovation of Muncipality Office, construction of compound walls etc.
Contractors
M/s. H. P. Madhukar,
Consultants
M/s. Vijaykumar Sawant Associates
Sub Works
This project involved 2 sub works. The details of the same available below
1
Illumination of main road from Forest Guest House to Police Quarters
100% completed
Project Duration
Stipulated Date of Commencement
July 03 2010
Stipulated Date of Completion /
Likely Date of Completion October 02 2010
Likely Date of Completion October 02 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,268,800.00
Awarded for
₹ 2,741,000.00
Contractors
M/s. James Electrical
Consultants
M/s. Vijaykumar Sawant Associates
2
Specialized hand painted tile cladding work
100% completed
Project Duration
Stipulated Date of Commencement
June 16 2011
Stipulated Date of Completion /
Likely Date of Completion September 15 2011
Likely Date of Completion September 15 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,817,618.00
Awarded for
₹ 4,797,750.00
Project highlights
Providing and fixing of hand painted tiles cladding for the seating provided on the Main road.
Contractors
M/s. Shilpi Constructions
Consultants
M/s. Vijaykumar Sawant Associates
See Similar Projects
Soft landscaping.
View Project
Upgradation of Infrastructure in Rural Areas Under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 -Construction of Panchayat Ghar V.P. Panchawadi.
View Project
Setting up of software technology park at Udyog Bhavan, Panaji, Goa- Dismantling civil and plumbing works
View Project