Project Duration
Stipulated Date of Commencement
January 02 2017
Stipulated Date of Completion /
Likely Date of Completion July 01 2017
Likely Date of Completion July 01 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,990,790.00
Awarded for
₹ 19,393,275.54
Project highlights
Work includes construction of pathways, gutters and other developmental works
Contractors
M/s. Race Constructions
Consultants
M/s. Nitin Arolkar