Project Duration
Stipulated Date of Commencement February 23 2014
Stipulated Date of Completion /
Likely Date of Completion
May 22 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,408,884.00
Awarded for ₹ 11,800,050.00

Project highlights

Compound wall made of concrete blocks and clay blocks.

 
Gallery Image
Contractors
M/s. Ahadh Engineering Construction
Gallery Image
Consultants
M/s Rahul Deshpande Assocaites
 
Similar Projects

See Similar Projects

Similar Project

Interior work for branch office of Directorate of Food and Drugs Administration in Old Collectorate building, Margao, Goa

View Project
Similar Project

Raising the Existing Compound Wall and Providing Additional Gutters

View Project
Similar Project

Construction of Forest Headquarters Building at Altinho Old IPHB Complex

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.