Project Duration
Stipulated Date of Commencement March 18 2019
Stipulated Date of Completion /
Likely Date of Completion
May 17 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 468,019.00
Awarded for ₹ 464,915.00

Project highlights

Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.

 
Gallery Image
Contractors
M/s. Vighneshwar Airconditioning Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Replacement of lifts at Goa Medical College including comprehensive AMC at Bambolim, Goa

View Project
Similar Project

Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Supply, Installation, Testing and Commissioning of 11KV 4 Way outdoor type RMU and other allied works

View Project
Similar Project

Upgradation of Primary Health Centre at Shiroda, Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.