Project Duration
Stipulated Date of Commencement February 27 2021
Stipulated Date of Completion /
Likely Date of Completion
August 26 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 291,308.00
Awarded for ₹ 291,308.00

Project highlights

Maintenance of UPS systems and servo stabilizers

 
Gallery Image
Contractors
M/s. Dubas Engineering Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Supply and Installation of Office Furniture

View Project
Similar Project

Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Dialysis Machine

View Project
Similar Project

Renovation/ Maintenance of Hospitals, CHCs, PHC’S, RMD’s under Directorate of Health Services in South Goa – S.H- Renovation/ Maintenance work of Primary Health Centre at Shiroda:Maintenance Contract of the Otis Make Passenger Elevator installed at PHC, Shiroda for the period of three years

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.