Project Duration
Stipulated Date of Commencement
June 06 2020
Stipulated Date of Completion /
Likely Date of Completion July 05 2020
Likely Date of Completion July 05 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 510,587.00
Awarded for
₹ 379,000.00
Project highlights
Supply and Installation of on-line UPS system of 10kVA capacity for Virology lab and batteries at Casualty, Ward 143, MS office, Lecture Hall and Examination Hall.
Contractors
M/s. Solar Enterprise
Consultants
In-house (GSIDC)