Project Duration
Stipulated Date of Commencement
February 13 2023
Stipulated Date of Completion /
Likely Date of Completion June 22 2023
Likely Date of Completion June 22 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,461,687.00
Awarded for
₹ 9,786,999.00
Project highlights
(SITC ) Supply, Installation, Testing and Commissioning of negative pressure VRDL Lab for GMC
Contractors
M/s. BIOXIA
Consultants
In-house (GSIDC)