Project Duration
Stipulated Date of Commencement
November 25 2016
Stipulated Date of Completion /
Likely Date of Completion November 24 2017
Likely Date of Completion November 24 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,345,311.00
Awarded for
₹ 5,75,64,205.00
Project highlights
Minor maintenance/Renovation works at Hospitals,Health Centres and Institutions
Contractors
M/s. Deshpande Constructions
Consultants
In-house (GSIDC)
See Similar Projects
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa-Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa.
View Project
Rural Medical Dispensary at Thane
View Project
Supply, installation, testing and commissioning of 13 Passenger with Stretcher Lifts at TB and Chest Disease Hospital, St.Inez – Goa
View Project