Project Duration
Stipulated Date of Commencement
December 30 2013
Stipulated Date of Completion /
Likely Date of Completion February 27 2014
Likely Date of Completion February 27 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 840,000.00
Awarded for
₹ 924,000.00
Contractors
M/S. VITEX MEDISYSYTEMS
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.