Project Duration
Stipulated Date of Commencement February 06 2014
Stipulated Date of Completion /
Likely Date of Completion
April 06 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,950,000.00
Awarded for ₹ 19,577,654.00
 
Gallery Image
Contractors
M/S. PHILIPS ELECTRONICS INDIA LTD
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa. -Civil works.

View Project
Similar Project

Supply, Testing and Commissioning of Intra Aortic Balloon Pumps

View Project
Similar Project

Construction of compound wall for the Goa Medical College, Hospital at Bambolim, Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.