Project Duration
Stipulated Date of Commencement August 26 2011
Stipulated Date of Completion /
Likely Date of Completion
November 25 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,725,185.00
Awarded for ₹ 3,581,610.75
 
Gallery Image
Contractors
M/s. Deshpande Constructions
Gallery Image
Consultants
M/s. Effective Architectural Services
 