Project Duration
Stipulated Date of Commencement
August 02 2011
Stipulated Date of Completion /
Likely Date of Completion July 11 2011
Likely Date of Completion July 11 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,158,024.00
Awarded for
₹ 6,849,926.00
Contractors
M/s. Vighneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Effective Architectural Services