Project Duration
Stipulated Date of Commencement
December 18 2007
Stipulated Date of Completion /
Likely Date of Completion March 01 2008
Likely Date of Completion March 01 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,667,482.00
Awarded for
₹ 2,508,525.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
See Similar Projects
Upgradation of NICU at Goa Medical College, Bambolim-Goa – Office Furniture
View Project
Supply, installation, testing and commissioning of 15 passenger cum bed lift for T. B. and chest diseases hospital, St. Inez, Goa.
View Project
Civil & Plumbing works (Phase-II) – Balance works.
View Project