Project Duration
Stipulated Date of Commencement
June 17 2006
Stipulated Date of Completion /
Likely Date of Completion June 16 2007
Likely Date of Completion June 16 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 118,993,540.00
Awarded for
₹ 135,678,880.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
Sub Works
This project involved 2 sub works. The details of the same available below
1
Furniture works
100% completed
Project Duration
Stipulated Date of Commencement
February 23 2008
Stipulated Date of Completion /
Likely Date of Completion May 07 2008
Likely Date of Completion May 07 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,927,260.38
Awarded for
₹ 27,788,946.00
Contractors
M/s. Knchan Associates
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
2
Providing of split air conditioners.
100% completed
Project Duration
Stipulated Date of Commencement
October 23 2008
Stipulated Date of Completion /
Likely Date of Completion November 06 2008
Likely Date of Completion November 06 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 726,404.00
Awarded for
₹ 762,190.00
Contractors
M/s. Blue Star Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. Maintenance /Renovation work of Sub District Hospital at Ponda, Goa – Repair of CCTV
View Project
Full Renovation And Part Construction Of The Old Heritage Building Of Asilo Hospital For State Health Training Institute At Mapusa. SH – External Lighting Work
View Project
– Office furniture and miscellaneous works.
View Project