Project Duration
Stipulated Date of Commencement February 11 2007
Stipulated Date of Completion /
Likely Date of Completion
November 10 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 51,241,559.00
Awarded for ₹ 71,828,955.90
 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Electrical works

100% completed
 
Project Duration
Stipulated Date of Commencement October 14 2008
Stipulated Date of Completion /
Likely Date of Completion
December 29 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,000,480.00
Awarded for ₹ 1,847,925.00
 
Contractors
Contractors
M/s.James Electricals
Consultants
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.
Similar Projects

See Similar Projects

Similar Project

Interior works

View Project
Similar Project

Supply Installation testing commissioning of AC system for New Library Bldg, GMC Complex, Bambolim, Goa.

View Project
Similar Project

Extension of R.M.O’s Hostel at Goa Medical College and Hospital, Bambolim Goa – Civil, Plumbing, Lifts, Electrical and Fire-Fighting Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.