Project Duration
Stipulated Date of Commencement
February 11 2007
Stipulated Date of Completion /
Likely Date of Completion November 10 2007
Likely Date of Completion November 10 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 51,241,559.00
Awarded for
₹ 71,828,955.90
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.
Sub Works
This project involved 1 sub works. The details of the same available below
1
Electrical works
100% completed
Project Duration
Stipulated Date of Commencement
October 14 2008
Stipulated Date of Completion /
Likely Date of Completion December 29 2008
Likely Date of Completion December 29 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,000,480.00
Awarded for
₹ 1,847,925.00
Contractors
M/s.James Electricals
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.
See Similar Projects
Maintenance/Renovation work of Community Health Centre – Sankhali Repair/Maintenance of HVAC system.
View Project
Mortuary Cabinet.
View Project
Minor maintenance/Renovation works at Hospitals,Health Centres and Institutions under Directorate of Health Services in the State of Goa.
View Project