Project Duration
Stipulated Date of Commencement December 14 2019
Stipulated Date of Completion /
Likely Date of Completion
December 13 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 57,329,858.55
Awarded for ₹ 43,924,239.85
 
Gallery Image
Contractors
M/S.VIPIN SHAH & ASSOCIATES.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – SH: Dismantling and buy back of existing Sewage Treatment Plant (STP) and Design, Supply, Installation, Testing and Commissioning of new 30 KLD STP at Community Health Centre, Canacona – Goa

View Project
Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Emerson make 40 KVA UPS system installed at Goa Medical College for three years

View Project
Similar Project

Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim – Goa -SH-Supply, Installation, Testing and Commissioning of Ventilators

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.