Project Duration
Stipulated Date of Commencement
May 19 2013
Stipulated Date of Completion /
Likely Date of Completion November 18 2014
Likely Date of Completion November 18 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 470,922,707.00
Awarded for
₹ 506,863,357.70
Contractors
M/s. Classic Contractors Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.