Project Duration
Stipulated Date of Commencement
September 02 2019
Stipulated Date of Completion /
Likely Date of Completion December 01 2019
Likely Date of Completion December 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,350,459.00
Awarded for
₹ 2,256,449.00
Contractors
M/s. Geeta Automation Technologies
Consultants
M/s. KICONS Limited