Status
Completed

Contractors

Consultants
Sub Works
This project involved 3 sub works. The details of the same available below
1
S.H. Carriage of Water
100% completed
Project Duration
Stipulated Date of Commencement
November 12 2013
Stipulated Date of Completion /
Likely Date of Completion November 11 2014
Likely Date of Completion November 11 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,025,750.00
Awarded for
₹ 2,044,000.00
Project highlights
Carriage of water from Altinho to Bambolim

Contractors
M/s. Deshpande Constructions

Consultants
In-house (GSIDC)
2
S.H. Carriage of Water
100% completed
Project Duration
Stipulated Date of Commencement
June 19 2017
Stipulated Date of Completion /
Likely Date of Completion June 18 2017
Likely Date of Completion June 18 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,115,875.00
Awarded for
₹ 8,619,018.75
Project highlights
Carriage of water from Altinho to Bambolim

Contractors
M/s. Pedro Gomes

Consultants
In-house (GSIDC)
3
S.H. Carriage of Water for 3 years
100% completed
Project Duration
Stipulated Date of Commencement
October 01 2018
Stipulated Date of Completion /
Likely Date of Completion September 30 2021
Likely Date of Completion September 30 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,347,625.00
Awarded for
₹ 25,844,737.50
Project highlights
Carriage of water from Altinho to Bambolim

Contractors
M/s. Pedro Gomes

Consultants
In-house (GSIDC)