Project Duration
Stipulated Date of Commencement
September 18 2019
Stipulated Date of Completion /
Likely Date of Completion September 17 2022
Likely Date of Completion September 17 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 378,000.00
Awarded for
₹ 343,800.00
Project highlights
Maintenance work
Contractors
M/s.Airflow Engineering
Consultants
In-house (GSIDC)
See Similar Projects
Networking, EPABX, UPS, Nurse Calling System, OPD System & Additional Electrical work.