Project Duration
Stipulated Date of Commencement
December 06 2018
Stipulated Date of Completion /
Likely Date of Completion December 05 2021
Likely Date of Completion December 05 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 64,500.00
Awarded for
₹ 64,500.00
Project highlights
Maintenance Contract of DG set for Three years
Contractors
M/s.Trinity Mahalasa Durga Sales and Services
Consultants
–
See Similar Projects
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College. S.H.: Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.
View Project
Supply Installation Testing & Commissioning of shadowless lamps, electro / mech hydraulic tables, etc. for Operation Theatre.
View Project
Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa SH: Maintenance/ Renovation Work of Sub District Hospital at Ponda, Goa – SITC of Split AC Units
View Project