Project Duration
Stipulated Date of Commencement
October 02 2011
Stipulated Date of Completion /
Likely Date of Completion November 15 2011
Likely Date of Completion November 15 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,010,827.44
Awarded for
₹ 6,303,000.00
Project highlights
Interior & Furniture works
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.