Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion June 15 2010
Likely Date of Completion June 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,960,000.00
Awarded for
₹ 20,00,000.00
Contractors
M/s. Thyssenkrupp Elevators (P) Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.