Project Duration
Stipulated Date of Commencement
May 18 2020
Stipulated Date of Completion /
Likely Date of Completion May 17 2023
Likely Date of Completion May 17 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 938,385.00
Awarded for
₹ 938,385.00
Project highlights
AMC of HVAC System
Contractors
M/s. Voltas Limited
Consultants
In-house (GSIDC)
See Similar Projects
Construction of Girls Hostel at Goa Medical College and Hospital, Bambolim, Goa.
View Project
Air Conditioning and Ventilation System
View Project
Medical gases & vacuum plant.
View Project