Project Duration
Stipulated Date of Commencement December 30 2005
Stipulated Date of Completion /
Likely Date of Completion
March 30 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,998,478.00
Awarded for ₹ 2,123,561.34
 
Gallery Image
Contractors
M/s. Deshpande Constructions
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Primary Health Centre at Navelim, Margao, Goa. – Supply, Installation, Testing & Commissioning of 200 A Distribution BOX.

View Project
Similar Project

Maintenance works of Goa Medical College and Hospital & Goa Dental College at Bambolim, Goa. SH – Carriage of water”

View Project
Similar Project

Channel Drainage Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.