Project Duration
Stipulated Date of Commencement
June 19 2023
Stipulated Date of Completion /
Likely Date of Completion August 02 2023
Likely Date of Completion August 02 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,405,012.00
Awarded for
₹ 1,303,226.76
Project highlights
Infrastructure for setting up of 6 Bedded Dialysis Unit
Contractors
M/s. Concept Creators
Consultants
M/s. Saolapurkar and Associates