Project Duration
Stipulated Date of Commencement
February 07 2015
Stipulated Date of Completion /
Likely Date of Completion February 06 2016
Likely Date of Completion February 06 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,480,851.00
Awarded for
₹ 97,176,913.14
Project highlights
Civil, Plumbing, Electrical, Lift & Fire – Fighting works.
1. The total bed capacity is 42.
2.The ground floor of the building shall have Casualty, 8 OPD’s & other rooms.
3.The first floor of the building shall have Operation theatre, Recovery room, etc.
Contractors
M/s. shilpi Constructions
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Supply, installation, testing and commissioning of Air Conditioners and ventilation system
View Project
Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Surgical Instruments
View Project
Construction of soak pits.
View Project