Project Duration
Stipulated Date of Commencement
February 07 2015
Stipulated Date of Completion /
Likely Date of Completion February 06 2016
Likely Date of Completion February 06 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,480,851.00
Awarded for
₹ 97,176,913.14
Project highlights
Civil, Plumbing, Electrical, Lift & Fire – Fighting works.
1. The total bed capacity is 42.
2.The ground floor of the building shall have Casualty, 8 OPD’s & other rooms.
3.The first floor of the building shall have Operation theatre, Recovery room, etc.
Contractors
M/s. shilpi Constructions
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College. S.H.: Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.
View Project
Supply, Installation and Testing and Commissioning of Patient Warming System
View Project
Hospital furniture work.
View Project