Project Duration
Stipulated Date of Commencement February 07 2015
Stipulated Date of Completion /
Likely Date of Completion
February 06 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 73,480,851.00
Awarded for ₹ 97,176,913.14

Project highlights

Civil, Plumbing, Electrical, Lift & Fire – Fighting works.
1. The total bed capacity is 42.
2.The ground floor of the building shall have Casualty, 8 OPD’s & other rooms.
3.The first floor of the building shall have Operation theatre, Recovery room, etc.

 
Gallery Image
Contractors
M/s. shilpi Constructions
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of Air Conditioners and ventilation system

View Project
Similar Project

Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Surgical Instruments

View Project
Similar Project

Construction of soak pits.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.