Project Duration
Stipulated Date of Commencement March 30 2017
Stipulated Date of Completion /
Likely Date of Completion
April 29 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,994,303.00
Awarded for ₹ 2,811,520.00

Project highlights

Providing furniture such as beds, compactors, racks, TV, Printer, Desks, etc.

 
Gallery Image
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, and RMDs under Directorate of Health Services in North Goa –S.H : Maintenance/Renovation work of Community Health Centre at Bicholim – AMC for 200kVA Transformer at CHC Bicholim for 3 years (2019-2022).

View Project
Similar Project

Interior work

View Project
Similar Project

Steel Operation Theatre.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.