Project Duration
Stipulated Date of Commencement
March 30 2017
Stipulated Date of Completion /
Likely Date of Completion April 29 2017
Likely Date of Completion April 29 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,994,303.00
Awarded for
₹ 2,811,520.00
Project highlights
Providing furniture such as beds, compactors, racks, TV, Printer, Desks, etc.
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
See Similar Projects
Lift work.
View Project
Rural Medical Dispensary at Keri.
View Project
Construction of New Hospital Block in place of existing Hospital for Institute of Psychiatry & Human Behaviour, Goa : Substation and allied works – Civil