Project Duration
Stipulated Date of Commencement
May 25 2018
Stipulated Date of Completion /
Likely Date of Completion July 24 2018
Likely Date of Completion July 24 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 727,500.00
Awarded for
₹ 623,850.00
Contractors
M/s. Techser Power Solutions Pvt Ltd
Consultants
In-house (GSIDC)