Project Duration
Stipulated Date of Commencement
August 19 2019
Stipulated Date of Completion /
Likely Date of Completion August 09 2019
Likely Date of Completion August 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 229,682.00
Awarded for
₹ 228,630.00
Contractors
M/S. Vighneshwar Airconditioning Pvt Ltd
Consultants
In-house (GSIDC)