Project Duration
Stipulated Date of Commencement September 14 2010
Stipulated Date of Completion /
Likely Date of Completion
November 23 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,341,483.24
Awarded for ₹ 18,900,000.00
 
Gallery Image
Contractors
M/s. Knchan Associates
Gallery Image
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa – S.H. Replacement of phase barrier sheets in HT panel of Megawin make and one time servicing of 33 KV HT outdoor breaker installed at Sub District Hospital, Ponda – Goa

View Project
Similar Project

Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Interior, Furniture works

View Project
Similar Project

S.H. Carriage of Water

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.