Project Duration
Stipulated Date of Commencement
September 14 2010
Stipulated Date of Completion /
Likely Date of Completion November 23 2010
Likely Date of Completion November 23 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,341,483.24
Awarded for
₹ 18,900,000.00
Contractors
M/s. Knchan Associates
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.