Project Duration
Stipulated Date of Commencement
December 19 2009
Stipulated Date of Completion /
Likely Date of Completion August 18 2010
Likely Date of Completion August 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,042,857.00
Awarded for
₹ 14,820,456.00
Contractors
M/s. Imperial Engineering Company
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.