Project Duration
Stipulated Date of Commencement
November 20 2019
Stipulated Date of Completion /
Likely Date of Completion November 19 2022
Likely Date of Completion November 19 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,612,007.00
Awarded for
₹ 2,612,007.00