Project Duration
Stipulated Date of Commencement March 26 2007
Stipulated Date of Completion /
Likely Date of Completion
June 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,196,784.00
Awarded for ₹ 1,185,000.00
 
Gallery Image
Contractors
M/s. Blue Star Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supplying Installation Testing & Commissioning of 33 KV VCB Isolation at Substation for Electrical Supply.

View Project
Similar Project

Supply Installation Testing & Commissioning of shadowless lamps, electro / mech hydraulic tables, etc. for Operation Theatre.

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. Maintenance /Renovation work of Sub District Hospital at Ponda, Goa – Repair of CCTV

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.