Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion August 25 2015
Likely Date of Completion August 25 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 377,910,694.72
Awarded for
₹ 415,663,311.00
Project highlights
Project consist of construction of school building, boys hostel and girls hostels for tribal community with capacity of 500 students.
Contractors
M/s. Harsh Construction Pvt. Ltd.
Consultants
M/s. Ulysis
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Sattari Taluka: Package-E (GPS Mhalshekarwada Parye, GPS Dhatwada Padoshe, GPS Rawan, GPS Gaonkarwada Honda, GHS Bhuipal)
View Project
Repairs/Upgratation & Maintenance of Govt Schools in the state of Goa – Package A (Sattari Taluka) – (GPS Gundelwada Velus, GPS Bhuipal, GPS Kopardem, GPS Dhamshe)
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Package N – Sattari Taluka – GPS Nanus, GPS Zarme,GPS Dabem, GPS Kumthol, GPS Karanzol, GPS Karmali Budruk) – Balance works.
View Project