Project Duration
Stipulated Date of Commencement
August 31 2017
Actual Date of Completion
June 26 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 29,480,548.00
Awarded for
₹ 32,564,020.00
Final Cost of Project
₹ -
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s Devang Constrction
Consultants
M/s Creative Abode