Project Duration
Stipulated Date of Commencement March 04 2014
Stipulated Date of Completion /
Likely Date of Completion
May 03 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,664,951.00
Awarded for ₹ 3,327,405.00

Project highlights

Fire Fighting work

 
Gallery Image
Contractors
M/s. Suchi Turnkey Pvt. Ltd.
Gallery Image
Consultants
M/s. KICONS Pvt. Ltd.
 