Project Duration
Stipulated Date of Commencement
June 20 2016
Stipulated Date of Completion /
Likely Date of Completion December 19 2016
Likely Date of Completion December 19 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,491,176.00
Awarded for
₹ 17,406,299.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.Jagdish V Pai
Consultants
M/s.Nitin Arolkar