Project Duration
Stipulated Date of Commencement
July 27 2013
Stipulated Date of Completion /
Likely Date of Completion July 26 2014
Likely Date of Completion July 26 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ 20,000,000.00
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. M.B. Kinlekar
Consultants
M/s. Datta kare associates
See Similar Projects
Repairs, Upgradation & Maintenance of Government schools in the state of Goa – Bicholim Taluka – Package M (GHS Amona, GPS Ambegal Pale).
View Project
Supply & Installation of Desks & Chairs for Government Schools/Colleges in the state of Goa- Part-III
View Project
Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project





