Project Duration
Stipulated Date of Commencement
November 05 2018
Stipulated Date of Completion /
Likely Date of Completion July 14 2019
Likely Date of Completion July 14 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,493,806.00
Awarded for
₹ 17,682,465.41
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Sandeep Khandeparkar
Consultants
M/s. Nitin Arolkar