Project Duration
Stipulated Date of Commencement
November 05 2019
Stipulated Date of Completion /
Likely Date of Completion March 18 2020
Likely Date of Completion March 18 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,910,469.00
Awarded for
₹ 2,082,601.80
Project highlights
Repairs/Upgradation & maintenance of School
Contractors
M/s. Saurabh M. Bakhale
Consultants
M/s. Manoj M. Amshekar