Project Duration
Stipulated Date of Commencement
June 28 2018
Stipulated Date of Completion /
Likely Date of Completion March 11 2019
Likely Date of Completion March 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,049,600.00
Awarded for
₹ 10,973,975.15
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode