Project Duration
Stipulated Date of Commencement
September 01 2006
Stipulated Date of Completion /
Likely Date of Completion September 01 2007
Likely Date of Completion September 01 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,881,225.00
Awarded for
₹ 6,030,626.00