Project Duration
Stipulated Date of Commencement
December 10 2018
Stipulated Date of Completion /
Likely Date of Completion August 24 2019
Likely Date of Completion August 24 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,535,793.84
Awarded for
₹ 8438797.59
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Manoj M. Amshekar