Project Duration
Stipulated Date of Commencement
March 07 2019
Stipulated Date of Completion /
Likely Date of Completion November 20 2019
Likely Date of Completion November 20 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,795,370.00
Awarded for
₹ 13,724,359.85