Project Duration
Stipulated Date of Commencement
March 07 2019
Stipulated Date of Completion /
Likely Date of Completion November 20 2019
Likely Date of Completion November 20 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,795,370.00
Awarded for
₹ 13,724,359.85
Project highlights
Repairs/Upgradation of School
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode.
See Similar Projects
Repairs/Upgradation & maintenance of Government schools in the state of Goa – Tiswadi taluka – Package-I (GPS Dhulapi, GPS Mangoda, GPS Gawant, GPS Akhada)