Project Duration
Stipulated Date of Commencement September 07 2018
Actual Date of Completion December 15 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,490,150.00
Awarded for ₹ 8,107,253.90
Final Cost of Project ₹ 5,750,282.89

Project highlights

Repairs/ Upgradation & Maintenance of schools

 
Contractors
M/s Nilambari Constructions
Consultants
M/s Allwyn Crasto
 