Project Duration
Stipulated Date of Commencement
February 13 2019
Stipulated Date of Completion /
Likely Date of Completion December 26 2019
Likely Date of Completion December 26 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,808,234.00
Awarded for
₹ 10,926,506.39
Project highlights
Repairs/Upgradation of School
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Creative Abode.