Project Duration
Stipulated Date of Commencement
August 29 2017
Stipulated Date of Completion /
Likely Date of Completion August 28 2017
Likely Date of Completion August 28 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,000,000.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.Rahul Constructions
Consultants
M/s.Manoj Amshekar (PMC)
See Similar Projects
Repairs/Upgradation and Maintenance of Government schools in the State of Goa -Civil, Plumbing and Electrical works -Salcete Taluka-Package D (GMS Khareband no.1, GPS Khareband no. 2, GMS Dramapur, GMS Oilemol Sao Jose de Areal)”
View Project
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka – Package H (G.P.S Kharekhajan- Virdi, G.P.S Kudchire, G.P.S. Pratap Nagar- Harvalem, G.H.S. Late Jayendra J. Rane- Kudchire)
View Project
Repairs/Upgradation & Maintenance Of Government Schools In The State Of Goa – Civil, Plumbing & Electrical Works – Package-I (Pernem Taluka) – Rate Contract
View Project