Project Duration
Stipulated Date of Commencement June 19 2021
Stipulated Date of Completion /
Likely Date of Completion
August 31 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 9,142,368.00
Awarded for ₹ 9,482,170.09

Project highlights

Construction of Government High School (annexe bldg) at Savai Verem , Ponda Goa
Designed with modern architectural looks.
Proposed building consists of Ground + 1 RCC framed structure.
The building will have vitrified flooring and Galvalume sheets sloping roof.
Provision for Aganwadi with kitchen & 2 classrooms with open courtyard on Ground Floor along with the toilet block.
Provision for Bal Bhavan, with Store room & 2 classrooms on First Floor along with toilet Block.
Total built up area of the building is 585.17 sqm.
Provision of shot blasted pavers along the periphery of the building.
The proposed new building will be constructed after demolishing the old structure.

 
Gallery Image
Contractors
M/s.UVR Developers
Gallery Image
Consultants
M/s.Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation & Maintenance of Govt. Schools in the state of Goa – Package C (Sattari Taluka) – (GPS Paikul, GPS Maigini, GPS Malpan, GPS Dhada Melauli, GPS Shel Melauli)

View Project
Similar Project

Repairs/Upgradation and maintenance of Government Schools in the state of Goa- Civil Plumbing and Electrical works:-Bicholim Taluka – Package K ( G.P.S Vathadev – Sarvan , G.P.S. Paltadwada, G.P.S. Naigini – Kudchire and G.P.S Kholpewadi – Sal )

View Project
Similar Project

Construction of new building and repairs of existing building for Government Higher Secondary School at Canacona – Erection of Distribution Transformer Centre (DTC) of 200 KVA

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.