Project Duration
Stipulated Date of Commencement
August 19 2019
Stipulated Date of Completion /
Likely Date of Completion April 18 2020
Likely Date of Completion April 18 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,016,611.35
Awarded for
₹ 18,098,805.51
Project highlights
Repairs, Upgradation & Maintenance work, civil, plumbing, Electrical etc.
Contractors
M/s. Shri. Mukesh Mandana
Consultants
M/s. Creative Abode